Page 196 - FINAL-book ประมวลกฎหมาย เกี่ยวกับการจัดซื้อจัดจ้างและการบริหารพัสดุ(แก้ไขครั้งที่15)
P. 196
Page 9
Volume 134 Special Part 210 D Government Gazette August 23, 2017
In order to make the and In order for the definition of particular specifications of
supplies to be procured to be at the standards and beneficial to the official service, if the
supplies to be purchased or employed already have announcement of industrial product
standards, the particular specifications of the supplies to be purchased or employ or lists of
the construction shall be specified in accordance with the Industrial product standard, or the
list of construction according to the industrial product standards, or for convenience, only the
standard numbers may be indicated. In the case that the supplies to be purchased or employed
do not have an announcement to define industrial product standard, but there is a person
registering such product with the Ministry of Industry, it prescribes that specification of
supplies to be purchased or employed shall be identified in the list of construction to be in
line with the specifications as specified in the purchaser manual or inserted purchaser manual
provided by the Ministry of Industry.
In contracting for construction, head of the State agency shall appoint a set of
committees or entrust an officer or any person to provide a construction plan or proceed for
contracting according to the provisions under Chapter 4 Design or Construction Work
Supervision.
Components, consideration period, and committee meetings under paragraph one
and paragraph two shall be as prescribed by the head of State agency as seen necessary and
expedient.
Procurement Reports
Clause 22. For each procurement method, apart from purchasing a land or
construction under Clause 23 and Clause 79 paragraph two, the officer shall provide a
procurement report and propose to the head of State agency for approval through the head
officer according to the following lists:
(1) Reasons and necessity for procurement;
(2) Scope of work or specifications of supplies or construction plans to be
procured, as the case may be;
(3) Focal price for the supplies to be procured;
(4) Procurement price estimation. The budget shall be indicated. In the case where
there is no such indicated budget, cost estimation can be set for such procurement;
(5) Duration for procurement;
(6) Selection method for consultancy work;
(7) Criteria for selection of proposal;
(8) Other proposals, such as request for approval of committee appointment
necessary for consultancy work, issuance of solicitation notifications and documents for
consultancy work.
For urgent case of procurement due to unexpected situations under Section 56
paragraph one (1) (c), or in the case where it is necessary to use such supply for emergency
case under Section 56 paragraph one (2) (d), or in the case where the procurement involves
such as small cost estimate according to the provisions prescribed in the Ministerial
Regulations issued in pursuance of Section 96 paragraph two of which the details cannot be
made into a normal report, the officer or person responsible for such matter shall provide
reports under paragraph one indicating only the lists that are necessary.