Volume 134 Special Part 210 D Government Gazette August 23, 2017
Clause 136. The provider is not allowed to use the construction plan settled into
contract with the employer for other construction projects, except for the case where written
approval is granted by the employer.
Clause 137. During the operation according to the procurement contract, the
employer may ask the provider of the construction design to revise some details in part that
does not have effect to material structure, which shall be in accordance with the construction
standards that the provider of construction design has delivered based on the work stages
specified in the contract without additional fees.
Clause 138. The provider of construction supervision work shall provide a
supervisor that has knowledge and skills suitable for such construction.
The provider of construction supervision work must submit the names of
construction supervisors, inspectors, or representatives to the employer for approval. In the
case where the supervisor cannot carry out duties specified under paragraph one, the provider
of construction supervision work shall propose a name of a representing supervisor. Such
representative in that case must be approved by the employer.
Part 2
Design or Construction Supervision Work Process
_________________
Provision of Draft for Design or Construction Supervision Scope of Work
Clause 139. For design or construction supervision work, the head of State agency
shall appoint a committee, or may entrust an officer or any person to be responsible for
providing a draft for design or construction supervision scope of work and specifying
selection criteria.
Components, period of consideration and committee meetings under paragraph one
shall be as prescribed by the head of State agency as seen necessary and appropriate.
Report for Design or Construction Supervision Work
Clause 140. For design or construction supervision work, the officer shall provide
report for the design or construction supervision work and propose to the head of State
agency for approval through the head officer according to the following lists:
(1) reasons and necessity for design or construction supervision work;
(2) scope of design or construction supervision work;
(3) qualification of the provider of design or construction supervision work;
(4) cost estimate for construction;
(5) approximate fees for design or construction supervision work;
(6) period of design or construction supervision work;
(7) method of design or construction supervision work and reasons for use of such
method;