Volume 134 Special Part 210 D Government Gazette August 23, 2017
In the case where it is necessary to provide explanation regarding the
design competition, such explanation shall be carried out on any business day. The State
agency shall provide the explanations to all providers no less than 7 business days prior to the
day of submission of proposals.
Date and time for tendering proposals shall be specified only one
business date and time by concerning a period for the providers to prepare construction
models;
(b) when it comes to the date to open proposal envelopes, the committee in
charge of construction design work by the design competition method shall review
documents of all service providers and select the providers who submit complete and correct
documents with design that is in line with the conditions prescribed in the documents for
construction design by the design competition method, and select the providers whose design
obtains the highest quality scores, and make the providers in order of the scores;
In the case where the selected provider obtaining the highest quality
scores does not settle into contract with the State agency within the time specified in the
documents for construction design work, the Committee shall consider the provider obtaining
the second highest quality scores instead;
(c) provide report of consideration results by applying the provisions under
Clause 114 (4) mutatis mutandis.
Clause 156. The provisions of Clause 118 shall be applied to the announcement
of successful tenderer for construction design work by the design competition method mutatis
mutandis.
Clause 157. The State agency may specify remuneration for the design
competitor under Step 2 who was selected under Clause 155 (2) (b) by concerning
appropriation and benefits to the official service. In this regard, the State agency shall also
inform of such remuneration in notifications and documents for construction design by the
design competition method.
Power to Order for Procurement of Design or Construction Supervision Work
Clause 158. Procurement for design or construction supervision work shall be
under the power of persons holding positions with cost estimate as follows:
(1) head of the State agency, not exceeding 50,000,000 baht;
(2) persons holding one level higher position, exceeding 50,000,000 baht.
The persons holding one level higher position under paragraph one shall be in
accordance with the account attached to this Regulation.
Clause 159. Any State enterprise requiring to specify competent persons and cost
estimate for procurement in pursuance of Clause 158 differently from what prescribed in this
Regulation shall propose to the Ruling Committee for approval. When the approval is
granted, such matter shall be informed to the State Audit Office of the Kingdom of Thailand.
Clause 160. Fees of design or construction supervision work shall be in
accordance with the rate specified in the Regulation issued in pursuance of Section 90
paragraph two.
236