Page 243 - FINAL-book ประมวลกฎหมาย เกี่ยวกับการจัดซื้อจัดจ้างและการบริหารพัสดุ(แก้ไขครั้งที่15)
P. 243
Page 56
Volume 134 Special Part 210 D Government Gazette August 23, 2017
In the case where the delivered supplies do not have specifications as indicated in
the contract or agreement, such matter shall be reported to the head of the State agency
through the head officer for acknowledgement and further order;
(5) in the case where the supplier or contractor delivers correct supplies but
incorrect amount, or the amount of supplies is correct, but not all the supplies are correct, if
the contract or agreement does not specify otherwise, only correct supplies shall be inspected
for acceptance by following the provisions under (4) and the officer shall report such matter
to the head of State agency through the head officer without delay to inform the supplier or
contractor of such matter within 3 business days from the day such problem is found without
prejudice for the State agency to request for a fine from the supplier or contract for such
incomplete or incorrect amount of supplies;
(6) inspection of supplies made in a series or unit, if any element is missing and
the supplies cannot work properly, it shall be deemed that such supplier or contractor has not
delivered such supplies. In general, the head of the State agency shall be reported of such
matter to inform the supplier or contractor within 3 business days from the day the problem is
found;
(7) in the case where some supplies inspection committee members do not accept
supplies by indicating objections to propose to the head of State agency for further
consideration and order, if the head of the State agency ordered to accept such supplies, the
committee members shall carry out the act under (4) or (5), as the case may be.
Clause 176. Supplies inspection committee for construction works shall have the
duties as follows:
(1) review qualifications of the construction supervisor of the contractor to be in
line with the Act on Building Controls;
(2) review the performance reports of the contractor and environmental
circumstances reported by the work supervisor of the State agency by weekly comparing to
the plan and regulations in the contract or agreement, including being acknowledged of
matters or consider for a leave of an employee, or suspension of the supervisor, and report to
the head of State agency for further operation;
(3) the supplies inspection committee or any committee member entrusted by the
supplies inspection committee shall conduct onsite inspection at the location of construction
work specified in the contract or agreement at appropriate time and shall provide a record of
such inspection for the evidential purpose;
(4) apart from the act under (1) and (2), in the case where there is a doubt or
where the plan and regulations in the contract or agreement have slightly shifted or do not be
in line with technical principles, the committee shall have power to order for additional
amendment or reduce details of work as seen appropriate and according to the technical
principles to be in accordance with the plan;
(5) generally, the inspection shall be conducted upon the work delivered by the
contractor within 3 business days from the day the Chairperson acknowledges of the work
delivery and such inspection shall be complete as soon as possible;
243