Volume 134 Special Part 210 D Government Gazette August 23, 2017
(6) if the work is correct and complete in accordance with the plan and regulations
specified in the contract or agreement, it shall be deemed that the contractor has completely
delivered the work on the day the contractor delivers such work and shall provide two copies
of a document certifying work performance for the whole or each stage, as the case may be,
with signatures affixed. The contractor and the officer shall keep one each to proceed for
payment requisition according to the Regulations on the Public Payment Requisition and
report such matter to the head of the State agency.
In the case where the supplies inspection committee see that the work delivered,
whether in whole or in stages, is not in line with the plan and the contract or agreement, the
committee shall report the head of State agency for acknowledgement or issuance of order, as
the case may be;
(7) in the case where some supplies inspection committee members do not accept
supplies by indicating objections to propose to the head of State agency for further
consideration and order, if the head of the State agency ordered to accept such supplies, the
committee members shall carry out the act under (6).
Clause 177. For the construction work which involves such gradual stages of
operations as to require close supervision thereof or which involves instalment payments in
accordance with the progress of the work, the head of State agency shall appoint a supervisor
who has technical expertise based on the type of construction work from government
officials, employees, government officers, university staff, public officers, or employees of
State agencies called by other names of such State agency, or government officials,
employees, government officers, university staff, public officers, or employees of State
agencies called by other names of other State agencies as being approved by the head of State
agency. In the case where the construction work requires knowledge and skills of various
fields, a supervisor specializing in particular fields or a group of supervisors may be
appointed.
The supervisor must possess qualifications as suggested by the designer and usually
possess not lower than the vocational certificate level.
In the case where it is necessary to employ a supervision provider to be a supervisor,
the employment can be proceeded by following the acts under Chapter 4.
Clause 178. The supervisor shall have duties as follows:
(1) inspect and supervise construction work at the location specified in the
contract or agreed to conduct such construction work every day to be in line with the
construction plan and the details in the contract. The supervisor may order to change, amend
or reduce work as seen appropriate and in accordance with technical principles to be in line
with the plan and the contract. If the contractor violates the order, the construction work,
either in part or in whole shall be paused, as the case may be, until the contractor complies
with the order. Such violation shall be reported to the supplies inspection committee or a
person entrusted to be responsible for contract or agreement administration and
constructional supply inspection for acceptance without delay;