Page 97 - FINAL-book ประมวลกฎหมาย เกี่ยวกับการจัดซื้อจัดจ้างและการบริหารพัสดุ(แก้ไขครั้งที่15)
P. 97

48


             acknowledging receipt of the application for the evidential purpose and consider the application
             without delay. When  the  State  agency has given  written  notification of  the  result  of  the

             consideration, the contractual party dissatisfied therewith shall have the right to initiate an action
             before the Court for further claiming damages under the contract. The rules, procedures and
             period of time for the consideration by the State agency of applications shall be in accordance

             with the Rule prescribed by the Minister, provided that it shall at least require the State agency
             to appoint a  committee  for  considering  damages and the  determination  of  the  amount  of
             damages required to be reported to the Ministry of Finance for consideration and approval.


                            Section 104.  In the case where a contract or an agreement in connection with
             procurement has been proceeded on the basis of a State agency’s failure to comply with this Act

             or a Ministerial Regulation, Rule or Notification issued under the provisions of this Act in any part
             dealing with immaterial matters or non-serious mistakes, the contract or agreement in connection
             with such procurement shall not be void.

                            The Policy Commission shall have the power to publish on an information network
             system  of the  Comptroller-General’s Department examples of  cases  deemed  to deal with

             material matters or serious mistakes or immaterial matters or  non-serious mistakes under
             paragraph one.
                            In the case where there arises any problem in connection with voidness of the
             contract or the agreement under paragraph one, any contractual party shall refer the matter to

             the Policy Commission for final decision.


                            Section 105.  Details as to methods and procedures for administration of contracts
             and inspection  of supplies  for acceptance  thereof  not  provided in  this Chapter shall  be in
             accordance with the Rule prescribed by the Minister.









             DISCLAIMER: THIS  TEXT HAS  BEEN PROVIDED  FOR  EDUCATIONAL/  COMPREHENSION PURPOSES  AND

             CONTAINS  NO LEGAL  AUTHORITY.  THE  OFFICE  OF THE  COUNCIL OF  STATE  SHALL  ASSUME  NO
             RESPONSIBILITY FOR ANY LIABILITIES ARISING FROM THE USE AND/OR REFERENCE OF THIS TEXT. THE

             ORIGINAL THAI TEXT AS FORMALLY ADOPTED AND PUBLISHED SHALL IN ALL EVENTS REMAIN THE SOLE
             AUTHORITY HAVING LEGAL FORCE.