Section 57. The details of procurement of supplies in this Chapter by an electronic
method on an information network system of the Comptroller-General’s Department shall be in
accordance with the Rule prescribed by the Minister.
Section 58. For the benefit of the public sector as a whole, any particular State
agency may conduct procurement of supplies for another State agency in accordance with a
framework agreement between the State agency conducting the procurement and a contractual
party.
In the execution of paragraph one, prime regard shall be had to the value for
money and purposes for use, in accordance with the Rule prescribed by the Minister.
Section 59. For the purpose of preparing draft terms of reference or details of the
supplies to be procured and draft solicitation documents prior to procurement of supplies by a
general solicitation notification method, a State agency may cause to be held the hearing of
opinions on draft terms of reference or details of the supplies to be procured and draft solicitation
documents from business operators.
The rules, procedures and period of time for the hearing of opinions on draft terms
of reference or details of the supplies to be procured and draft solicitation documents to be used
as solicitation documents shall be in accordance with the Rule prescribed by the Minister.
Section 60. Prior to procurement of construction work by a method under section
55, a State agency shall make available a plan for the construction work. In this regard, the State
agency may intend to draw up the same by itself or conduct procurement in accordance with
Chapter VIII, Design or Construction Supervision Work.
In the case where there must be procurement of a design together with the
construction in respect of which a plan for the construction work may not be made available
under paragraph one, the proceeding under paragraph one may be exempted. The question as
to in which case procurement of a design together with the construction shall be conducted shall
also be considered in the light of appropriateness of the project and cost estimate therefor. In
DISCLAIMER: THIS TEXT HAS BEEN PROVIDED FOR EDUCATIONAL/ COMPREHENSION PURPOSES AND
CONTAINS NO LEGAL AUTHORITY. THE OFFICE OF THE COUNCIL OF STATE SHALL ASSUME NO
RESPONSIBILITY FOR ANY LIABILITIES ARISING FROM THE USE AND/OR REFERENCE OF THIS TEXT. THE
ORIGINAL THAI TEXT AS FORMALLY ADOPTED AND PUBLISHED SHALL IN ALL EVENTS REMAIN THE SOLE
AUTHORITY HAVING LEGAL FORCE.
79